DIKSHA – Solution Testing Process & Timelines
Last Updated On May 25, 2021

Download Templates
Testing Timelines
Release Plan – 4.0
| Environment | Start Date | End Date |
|---|---|---|
| Staging | 3rd June 2021 | 11th June 2021 |
| Pre Production | 14th June 2021 | 18th June 2021 |
Release Plan – 4.1
| Environment | Start Date | End Date |
|---|---|---|
| Staging | 12th July 2021 | 19th July 2021 |
| Pre Production | 20th July 2021 | 23rd July 2021 |